Applicant Legal Entity: YERSON ENERJİ ELEKTRİK ÜRRETİM ANONİM ŞİRKETİ
Production Facility and/or Project Name: İvme Bendi ve HES
Production Facility and/or Project Province/Provinces: Batman Province
Total Installed Power of the Production Facility (ISO Standards): 178,500 MWm 173,085 MWe
Production Facility Type: Reservoir (no active volume)
Energy Source: Hydraulic
Turbine Type: Kaplan
Unit Number: 8 x 3 units = 24
Unit Installed Powers:6 x 3 x 5,727 MWe + 1 x 3 x 9,880 Mwe + 1 x 3 x 13,453 Mwe= 173,085 MWe 6 x 3 x 5,910 MWm + 1 x 3 x 10,180 MWm + 1 x 3 x 13,860 Mwm= 178,500 MWm
Annual Production Amount It Can Produce with Its Current Installed Power: 486,170 GWh
System Connection Point and Voltage Level: Batman TM, 154 kV
Current Physical Status of the Production Facility: In the project phase
Stream Name: Batman Stream
Production Facility Reserve Flood Level: 592.15 m
Production Facility Maximum Tail Water Level: 525.00 m